Answer: D. 2.2%
Explanation: Equity Dividend Rate is calculated by dividing the Before Tax Cash Flow by the Acquisition price. If you need the answer in percentage form, you then multiply by 100.
Here, before-tax cash flow = $11,440
Acquisition price = $520,000
So Equity Dividend Rate =
X 100
Equity Dividend Rate = 2.2%
In this question, you do not need the Net Operating Income (NOI). You only need the NOI if the Before Tax Cash Flow is not given and the debt service payment is. If this is the case, you subtract the debt service payment from the NOI to get the Before Tax Cash Flow.
Answer:
Objective function:
Maximize Z: 30P1 + 25P2 + 28P3
Subject to: 2.00P1 + 1.50P2 + 3.00P3 ≤ 450 (Department A constraint)
2.50P1 + 2.00P2 + P3 ≤ 350 (Department B constraint)
0.25P1 + 0.25P2 + 0.25P3 ≤ 50 (Department C constraint)
P1, P2, P3 ≥ 0 (Non-negativity)
Explanation:
The objective function is formulated from the contribution margin of the three products. For instance, the contribution of Product 1 is $30, the contribution of Product 2 is $25 and the contribution of Product 3 is $28. Thus, the objective function will be 30P1 + 25P2 + 28P3.
The constraints were obtained from the departmental labour hours requirements for each product. For instance, Product 1 requires 2 hours in department A, Product 2 requires 1.50 hours in department A and Product 3 requires 3 hours in Department A. Thus, the constraint will be 2.00P1 + 1.50P2 + 3.00P3.
Answer:
Purchase Decision Process
Explanation:
The purchase decision process is the one through which the a buyer makes his decision of buying a certain product.
This consumer buying process has five step which they use to make their decision, are following;
- Need or Problem Recognition.
- Information Search.
- Evaluation of Alternatives.
- Purchase Decision.
- Post-Purchase Evaluation.
I hope the answer is helpful.
Thanks for asking.
Answer:
The Correct statement is option B. The decision of the company not to adjust for risk means that the company will have to accept too many projects in the office furniture manufacturing division and too few in the data processing division.
Explanation:
Based on the information given the decision of the company not to adjust to the risks will lead to the firm accepting project that are too many in the office furniture Manufacturing Divsion while that of data processing Division will accept too few project, which means that the firm will be at risk in a situation where they want to raise the cost of capital reason been that the company cash flow will be Discounted by the investor at a rate that is high which will inturn Lead to the company value to decline.
Therefore The Correct statement is option B.
Answer:
$6.3 per share
Explanation:
There are two method of Valuation of the firm
- Weighted average cost of the capital (WACC)
- Free cash flow to equity (FCFE)
We have to calculate the value of the firm using FCFE. Free cash flow to equity (FCFE) is the amount of cash flow generated by the business and potentially available for distribution among the stockholders.
Value of firm = Free cash flow / required rate of return = $120,000 / 12% = $1,000,000
Market value of Equity = Total value of firm - Market value of Debt - Market value of Preferred share
Market value of Equity = $1,000,000 - $300,000 - $70,000 = $630,000
Value of Patrick's stock = Market Value of equity / shares of stock outstanding = $630,000 / 100,000 = $6.3 per share