Answer:
The annual depreciation cost the facility will rise by 10% or $4,000,000.
Explanation:
Annual depreciation = 
Annual depreciation = 
Annual depreciation = 10% or $4,000,000
Answer:
d- EVP has a short-term swing profit is $3000
Explanation:
Lets first understand what short-term swing profit is. Short-term swing profit is profit dependent upon a rule normally set by the securities & exchange commission which states that any profits made by company insiders through the purchase and sale of share/stocks within six months must be returned to the company. Company insiders are people/employees working within the entity mostly having more than 10% of company's shares or employees such as executives, directors and managers.
Now It's not clear from the question what the purchase price of the shares was when EVP sold them on January 12 2016, assuming these shares were purchased at $20, then the short-term swing profit would be $2000 as at January. Then EVP purchases 100 shares at $20 and sells them at $30 per share as at june. The additional short-term swing profit would be $1000 (i.e $30-$20=$10 per share).
Therefore the total short-term swing profit is $3000
Answer:
c. $64 million
Explanation:
For computing the revenue recognized, first we have to determine the percentage which is shown below:
= Cost incurred in 2014 ÷ expenses incurred
= $48 million ÷ $120 million
= 40%
And, the contract price is $160 million
So, the revenue recognized would be
= Contract price × percentage
= $160 million × 40%
= $64 million
Answer:
The total overhead variance in hours taken is 3,600 hours
The total overhead cost variance is $1,110
Explanation:
The variance is about the different between budget/ standard and actual figures.
Standard hours allowed for the work done is 22,200 hours; and the predetermined overhead rate is $5.75 per direct labor hour. So total cost budgeted for work done is $127,650 = $5.57 x 22,200 hours
The total overhead variance in hours taken = standard hours of 22,200 - actual direct labor hours of 18,600 = 3,600 hours
The total overhead cost variance = standard cost - actual cost = $127,650 - $126,540 = $1,110
Answer:
The correct answer is A
Explanation:
The current liabilities is computed as:
Current Assets (CA) = Quick assets (QA)+ Inventory (I)
CA = QA + $49,000
Acid test ratio = Quick assets / Current Liabilities (CL)
2.8 = QA / CL
QA = 2.8 × CL
Current Ratio (CR) = CA / CL
3.5 = CA / CL
Putting CA = QA + Inventory
3.5 = ( QA + $49,000) / CL
Now, Putting QA = 2.8 × CL
So,
3.5 = [( 2.8 × CL ) + $49,000] / CL
3.5 = 2.8 CL / CL + $49,000 / CL
3.5 = 2.8 + ($49,000 / CL)
3.5 - 2.8 = $49,000 / CL
0.7 = $49,000 / CL
CL = $49,000 / 0.7
CL = $70,000