Answer: The risk of stock out = 2.94%
Explanation:
Reorder point is calculated as: Lead time*demand per unit time=45*9=405
While the amount on-hand reaches 422 pounds, the manager was reordering lubricant.
During the lead time, Standard Deviation of Demand =Daily S.D*(Lead time)^0.5=3*(9^0.5)=9
Risk of Stock Out=(422-405)/9 S.D=1.89 S.D
From Normal distribution curve 1.89 S.D=0.0294=2.94%
Therefore, the risk of stock out=2.94%
Answer:
The correct word for the blank space is: the purchases history.
Explanation:
Purchases history allows businesses to have an idea of what the preferences of its customers are or how they can change over time. It is a helpful tool firms can use to offer similar or complementary products that may be of interest to their customers and that may end up increasing the organization's revenues if the consumer makes the additional purchase.
Answer:
$32,647
Explanation:
P=R(1-(1+i)^-n)/i
Where P=$140,000
R=?
i=14%
n=7 years
by putting above values in formula, we get
140,000=R (1-(1+.14)^-7)/.14
$140,000=R4.288
R=$140,000/4.288
R=$32,647
Answer:
Mointaintop should charge 84.18 dollars per round of golf to achieve his desired return.
Explanation:
return:
50,000,000 x 12% = 6,000,000
fixed cost: 24,000,000
Variable cost: 16 per golfer
golfers expected 440,000
It should price to pay up the variable cost, fixed cost and achieve the 12% return:





S = 84,18181818181818
It should charge per round 84.18 dollars
Answer:
11.2 containers
Explanation:
The computation of the number of kanban connectors needed is given below:
= (Lead time demand + Safety stock) ÷ Container size
where,
Demand during Lead time demand is
= 1,400 units × 3 days
= 4,200 units
Container size = 500 connectors
Safety Stock is
= 1 day × 1,400 units
= 1,400 units
So, the number of kanban connectors needed is
= (4,200 units + 1,400 units) ÷ (500 units)
= 11.2 containers
We simply used the above formula