Answer:
$422.5
Explanation:
Assessable value after first homestead exemption $25000= $200000
Tax on second $25000=$267.5($112.5 school board tax+$95 county tax +$60 citty tax)
Tax on third $25000=$112.5(onl on school district tax)
Tax on balance = $10.7*150=$1605
Total tax =$1985
Money saved= $267.5+$155=$422.5
A parameter is a value that the user enters whenever a query is run, which provides flexibility, enables user to access information easily, and costs less.
Hope this helps :)
~Davinia.
Answer:
$2,000 and it is favourable
Explanation:
Direct material quantity variance is defined as the efficiency with which materials are converted into products. It is calculated by multiplying standard price of material by the difference between standard quantity and actual quantity used.
Standard price (SP)= $2.50
Standard quantity (SQ)= 30,000 units
Actual quantity (AQ)= 29,200 units
Material quantity variance = SP * (SQ - AQ)
Material quantity variance= 2.50 * (30,000 - 29,200)
Material quantity variance= $2,000
Answer:
Given that,
Cost of goods manufactured = $1,486,000
Cost of goods sold (unadjusted) = $1,337,000
Therefore, the journal entry for the transfer of completed goods from WIP to Finished goods is as follows:
Finished Goods A/c Dr. $1,486,000
To Work in process $1,486,000
(Being transfer of completed goods from work in process to finished goods recorded)
Answer:
Law of effect
Explanation:
This law was developed by Edward Thorndike
When Responses are followed by satisfaction, it causes people to become more attached to a situation. This is likely going to cause these people to continue doing things as they are doing them now. This is why if Carly uses positive reinforcement, her employees will do their jobs same way they are doing it now.
Conversely, if the situation is followed by discomfort, that is she uses punishments or extinction, the
employers will disconnect themselves from doing their jobs the same way they have been doing it.