Answer:
Total= 20 potatoes + 2 steaks
Explanation:
Giving the following information:
Her budget is $30 for every 10 days and she must buy enough potatoes to eat at least 2 potatoes per day. If a potato costs $0.50 and the price of a steak is $10.
2 potatoes a day= 0.5*2= 1
Consumption of potatoes= 10 days*$1= $10
Consumption of steak= 30 - 10= 20/10= 2 steaks.
Total= 20 potatoes + 2 steaks
Correct/Complete Question:
What is the time of the slowest workstation in a production system?
A. utilization
B. bottleneck time
C. effective capacity
D. throughput time
Answer:
B, bottleneck time
Explanation:
A bottleneck in a production system refers to a constraint in the production system where supply takes the longest time to meet up with demand for a particular good.
In the production processes, bottleneck time is the time takencapacity of the ful in a certain process of production as a result of the limited capacity of the process, thereby reducing the entire production chain.
Simply put, a bottleneck is a delay in time of one of the production process thereby slowing down the entire production system.
Cheers.
Answer:
The correct option is B
Explanation:
Inflation is the measure which is quantitative in nature as the rate at which the average level of price of the selected goods and services in the economy rises over the year or time period.
It is stated or expressed in terms of percentage, because it indicates or explains the decrease or fall in the purchasing power of currency of the nation.
So, if the inflation is higher than what is expected, then the creditors who invested their money, will receive lower rate of interest then they anticipated as their is decrease of fall in the currency of the nation.