Answer:
D. Inflation factors to actual costs incurred by the contractor
Explanation:
The effect of inflation on the profitability of a product cannot be overemphasized. At the time of inflation the profitability of a project will be reduced and the cost of capital will increase. The effect of inflation on a project can be determined by applying inflation factor.
Inflation impacts on the cash flow from a project, especially a project with a long life span.
Answer:
the $500,000 that the old production line costed must be treated as a sunk cost. Sunk costs are costs that have already been incurred and the firm cannot recover them no matter what they do. in this case, since ankle-length skirts are out of fashion, the production is useless and is worth $0.
Explanation:
Answer:
B. 14
Explanation:
ES = early start
ES = finished point of the predecessor activity
Considering we have two activities which are:
5-7 which is expected to start at 6 and finish in 5 thus It will end at 11
6-7 which is expected to start at 7 and has a duration of 7 thus, ending at 14
The 7-8 activity will start as soon as the precedecessor end. These activities are finished at point 14 thus, that is the earliest activity 7-8 can start.
Answer:
Realistic aspect
Explanation:
Considering the scenario described in the question it can be concluded that Cosmo shifted his focus onto which REALISTIC aspect of goal-setting theory.
This is because following Cosmo making his dream come true of buying the property that his restaurant occupies, the idea that he could rent out the storefront next to the restaurant for added income is a REALISTIC Aspect of Goal Getting.
This implies that Cosmo is more realistic in terms of his financial abilities and willingness to work toward the goal of paying off the mortgage loan
Answer:
$1000
Explanation:
Total factory rent is $2500 for 5000 sq ft. The basis for assigning the rent cost to different activities will be on the basis of factory area used.
Factory area used by different activities is as follows,
1. Machining 500 sq ft
2. Preparation & Setup 2000 sq ft
3. Quality Control 2000 sq ft
4. Finishing 500 sq ft
So, The cost that will be assigned to the Preparation and setup cost will be
$2500 * 2000/5000 = $1000