Three workers per day is minimum resource limit.
<u>Explanation:</u>
Every day he needs maximum of 3 workers, so this can be set of the minimum resource limit for the project.
Thus, the minimum resource limit for the project is - Three workers per day
All asset make and change demands are assessed against each LimitRange object in the task. In the event that the asset abuses any of the listed requirements, at that point the asset is dismissed. In the event that the asset doesn't set an express worth, and on the off chance that the imperative backings a default esteem, at that point the default esteem is applied to as far as possible is an edge for an asset the executives and helps control asset use. A procedure for overseeing limits takes into consideration the reallocation of assets to various clients or activities as necessities change.
Answer:
a. Sep 10
b. $21,823
c. $21,500
Explanation:
a) Due date of the note
July 13 to 31 = 19 days
Aug 1 to 31 = 31 days
Sep 1 to Sep 10 = 10 days
due date is Sep 10
b) Maturity value of the note
$ 21500 + $ 21500*9%*60/360
= $ 21823
c) Journal entry
Cash debit $ 21823
interest recieved credit $323
Notes Receivable credit $ 21500
B
jwxjedexececrctcrctctctctvtvtvt
Answer: 8.60%
Explanation:
Given the following :
Current debt-equity ratio = 0.52
Target debt-equity ratio = 0.45
Cost of floating equity = 9.5%
Floatation cost of debt = 6.6%
The Weighted average cost is calculated by finding the Weighted average cost of both debt and equity.
1 + 0.45 = 1.45
Weight of debt= 0.45/ 1.45 =0.31034
Weight * cost of debt
0.31034 × 6.6% = 2.0482758
Weight of equity = 1/1.45 = 0.6896551
Weight * cost of equity
0.6896551 × 9.5% = 6.5517241
Sum of both
(6.55 + 2.05) % = 8.60%