Answer:
210 hours
Explanation:
The learning curve rate can be found by log75%
Ln0.75 = 0.12249
1 batch requires 200 hours
The 1500 units batch will require 200 hours
For 3000 units there will be two batches of 1500 units each
200 hours * 2 batches * 0.12249 * 4.5 = 210 hours
Answer:
See explanation Section
Explanation:
See the image to get the appropriate answer.
Answer:
Bob Johnson, you know, I had a friend named Bob. Those were the days.
Explanation:
Answer: $0
Explanation:
Forward contracts get their value from the cost and on December 1, there was no cost to Curtis as he Curtis had just signed the contract.
This means that the amount that should be recorded for the Forward Contract should be $0. Even though the contract is valued at $0, it will still need to be credited against the amount to be received to at least recognize that a forward contract was entered into.
Answer:
FCFE: 99
Explanation:
FCFE: cash flow from operation - CAPEX + borrowing
we calcualte the cash flwo form operation using the indirect method:
net income - preferred dividends = available for common stock
income = 125 + 14 = 139
net income 139
depreciation expense 50
change in working capital (30)
cash flow from operation: 159
CAPEX will be the long term assets investment
investment on fixed capital<u> 100 </u>
CAPEX 100
net borrowing 40
159 -100 + 40 = 99