Well, from what you’ve posted, it seems that a negative value cannot be accepted since that would imply she has gone underwater. She also cannot go above 300 feet since she is going downwards from a max height.
Standard deviations of the four activities of the critical path are 1,2,4,2.
Standard deviation of this critical path = Sum of square root of variance of this corresponding critical path
Standard deviation of critical path 



Now we need to find the probability that the project will completed in 38 weeks given that its expected completion time is 40 weeks.
That is, we need to find P(X<38) :


Probability 
Thus the probability that the project will be completed in 38 weeks is 0.34.
Answer:
A)Percentile for Lynette, the student who is 65 in. tall is 36th
B) Asher is 22 inches tall.
Step-by-step explanation:
Percentile : It is a measure used in statistics indicating the value below which a given percentage of observations in a group of observations falls
A) Find the Percentile for Lynette, the student who is 65 in. tall.
No. of students below 65 inch =9
So, Percentage of data below 65 inch =
So, Percentile for Lynette, the student who is 65 in. tall is 36th
B)Ashers height is at the 88th percentile of the distribution. Interpret this value in context. How tall is Asher

22=x
So, No. of students below or st 88th percentile = 22
So, Asher is 22 inches tall.
Answer:
The average rate of change of f(x) = 3.14 inches⁻¹
The change in f(x) = 49.32 in
Step-by-step explanation:
The surface area of the spherical sculpture = x and its diameter f(x) = πx.
The average rate of change of f(x) as x changes is df(x)/dx = π = 3.14
Now the change in diameter Δf(x) = df(x) = (df(x)/dx)dx = πdx
dx = Δx = 28.3 in² - 12.6 in² = 15.7 in²
df(x) = π × 15.7 = 49.32 in