Answer:
Compensate for the risk
Explanation:
In the context of the scenario given , risk is defined as a form of exposure to a potential dangerous situation.
It is necessary for any person organization facing a risky situation to look for ways of minimizing or avoiding the risk in order to reduce related losses. Risks can be avoided through transfer , rejection , delayed action and compensating the risk,
The method of risk aversion described in the scenario is to compensate the risk.
Compensating the risk is a risk control method of using an alternative means to achieve a particular purpose in order to avoid the related risks to using the initial method.
Answer:
Project 1, 2 and 3 should be rejected.
Explanation:
This problem required us to tell which project we should not accept. To solve this we have to apply this rule that is accept the project with positive NPV.
The detail calculation are given below.
The discount factors to be used for CFO, CF1, CF2 and CF3 is 1, 0.74, 0.55 and 0.41 respectively. It is calculated by using following formula.
DF= (1 + i)^-n (n is period and i is 35%)
So now calculating NPV of each project by multiplying cashflow with discount factor.
Project 1 = -100+ (50*0.74 ) + (50*0.55) + (50*0.41) = -15 M dollars
Project 2 = -80 + (40*0.74) + (45*0.55) + (50*0.41) = -5.15 M dollars
Project 3 = -70 + (30 *0.74) + (40*0.55) + (50*0.41) = -5.3 M dollars
Project 4 = -60 + (30 *0.74) + (40*0.55) + (60*0.41) = 8.8 M dollars
Project 5 = -50 + (25 *0.74) + (30*0.55) + (70*0.41) = 13.7 M dollars
Answer
The answer and procedures of the exercise are attached in the following archives.
Explanation
You will find the procedures, formulas or necessary explanations in the archive attached below. If you have any question ask and I will aclare your doubts kindly.
Answer:
<u>Night Lights $ per unit 2.13</u>
<u>Desk Lamps $ per unit 8.50</u>
Explanation:
Determine total number of budgeted direct labour hours for the year
total number of budgeted direct labor hours for the year is calculated
= night lamp labor hours + desk lamp labor hours
= ( 60000 * 1/2 ) + ( 80000 * 2 )
= 30000 + 160000
= 190000
calculated the single plant wide factory overhead rate
factory overhead rate = total factory overhead / total number of budgeted unit
= 807500 / 190000
= 4.25 per labour hour
calculate factory overhead cost per each unit
night lamp = 4.25 * 1/2
= 2.13 per unit
desk lamp = 4.25 * 2
= 8.50 per unit