Answer:
The correct answer is both A and C
Explanation:
Solution
Given that:
The Process 1 Registration, Capacity = 0.5 registration per minute (1/2)
The Process 2 Cashier, Capacity = 1*3 / 10 = 3/10 = 0.3 payments per minute
The Process 3 , Photo ID, Capacity = 1*4 / 20 = 0.2 ID per minute
Now
The Time taken for process a unit is minimum of Demand rate / Lowest process capacity
so, the flow rate = 0.2 student per minute or 5 minute per student
Thus,
The total time = 20 * 5 = 100 minutes.
Barcelona's more relaxed work rules could help it achieve relational coordination - <span>the social processes and the human interactions support the coordinating process and task integration. The relational coordination includes communication and relationships in order to achieve the same goal.</span>
Answer:
the yield to maturity is 5.49%
Explanation:
Consider the following calculations
Yield to Maturity = [Interest + (Price - Redeemable Value)/n] / (Price + Redeemable Value)/2 = [32.25 + (1034 - 1000)/8] / (1034 + 1000)/2 = 2.745% semi-annually
Annually = 2.745 x 2 = 5.49%.
Answer:Hello there! i am figuring this question out for you!
Explanation:
Answer:
$0.67 per direct labor-dollar
Explanation:
Given that,
Direct labor-dollars to support all productions = $8,370,000
Fixed overhead cost = $5,022,000
Variable overhead cost per direct labor-dollar = $0.07
Predetermined overhead rate:


= 0.07 + 0.6
= $0.67 per direct labor-dollar