Answer:
360
Explanation:
Kanban is a method that is used to mange workflow in order to assist in visualizing the work and maximize the efficiency of a workers as well as making the workers agile.
The formula for calculating the number of Kanban is given as follows:
Number of Kanban = (Dd × LT × (1 + SS)) ÷ QC .................. (1)
DD = Daily required production level = 250
LT = Lead Time (in minutes) = 30
SS = Safety Stock = 20% = 0.2
QC = Number of squidgets in a container = 25
Substituting the values above into equation (1), we have:
Number of Kanban = (250 × 30 × (1 + 0.2)) ÷ 25
= (250 × 30 × 1.2) ÷ 25
= 9,000 ÷ 25
= 360
Therefore, the number of kanbans to be circulated between Sandy's process and the previous operations is 360.
Answer:
pooled task interdependence.
Explanation:
This is the most interdependent type. Although each business unit accomplishes separate tasks, they provide contributions to the main common goal. If one part fails, the whole project or goal may also fail. While working independently, team members still share loose or unstructured responsibilities to achieving goals.
Answer:
880 blue ink pens
Explanation:
The computation of the inventory position is shown below:
= Current stock counted in the closet + already placed orders with the supplier
where,
Current stock counted in the closet is 220 blue ink pens
And, the already placed orders with the supplier is 600 blue ink pens
Now placing these values to the above formula
So, the inventory position is
= 220 blue ink pens + 600 blue ink pens
= 880 blue ink pens
Answer:
a. What is the expected value of unit sales for the new product? (Do not round intermediate calculations and round your answer to the nearest whole unit.)
Possible Market Reaction Sales Units Probability Expected sales
Low response 20 .30 6
Moderate response 35 .20 7
High response 50 .20 10
<u>Very high response 90 .30 27 </u>
Total 50 units
b. What is the standard deviation of unit sales? (Do not round intermediate calculations. Round your answer to 2 decimal places.)
mean = (6 + 7 + 10 + 27) / 4 = 12.5
variance = {[0.30 x (20 - 50)²] + [0.20 x (35 - 50)²] + [0.20 x (50 - 50)²] + [0.30 x (90 - 50)²]} / 4 = (270 + 45 + 0 + 480) / 4 = 795 / 4 = 198.75
standard deviation = √198.75 = 14.10 units