What John’s company should prepare to demonstrate is the
best practices that they are engaging in managing how it impacts the
environment as this is a way of complying or keep up with the top management request
and when they undergo with the review.
Answer:
The endowment fund is not satisfied with the advisor's performance
Explanation:
Judging from a nominal interest rate perspective where return expected of an investment comprises of real rate of return and an extra return which is a compensation for inflation rate in the economy,the endowment fund is not satisfied with performance of the advisor.
The satisfactory rate of return that would be expected of the advisor is computed below:
nominal interest rate=real rate+inflation rate
real rate is 8.2%
inflation rate is 2.9%
nominal interest rate=8.2%+2.9%
=11.10%
Answer:
A. Decrease net capital outflow
B. Increase in net exports
C. Decrease in net exports.
D. Increase net capital outflow.
Explanation:
A. When the Sony pension fund buys U.S treasury then there is a inflow of capital. Hence, this will decrease the net capital outflow.
B. The Sunkist oranges is purchased by the South Korean tourist from the american farmer will increase the exports of the U.S. Hence, there is an increase in the net exports.
C. When a Toyota is purchased by an American then this will increase the imports of United states and hence, there is a reduction in the net exports.
D. The shares of Sony are purchased by an american, so there is a outflow of capital and this will increase the net capital outflow.
Answer:
The BCWS is also known as Planned Value (PV).
So, in this way, <em>PV = 3.125.000</em>
Explanation:
With the data we can obtain the PV as follows:
First, let's calculate EV as EV = CV + AC.
EV = -500.000 + 4.000.000 = <em>3.500.000</em>
After this, we can calculate PV with this formula: SPI = EV/PV
PV = EV/SPI
PV = 3.500.000/1.12 = <em>3.125.000</em>
<em />
<em>We can conclude, with these results, that the project actually is forward about the schedule but with an overcost about the budget. In other words, the project advance must be 41% but now is on 36% due to the negative variance on the costs (CV).</em>
<em />
Answer:
$500 favorable
Explanation:
Given;
Number of units produced = 10,800 units
Actual indirect material costs = $13,000
Reflected indirect material costs for 144,000 units = $180,000
Now,
Per unit reflected indirect material costs = $180,000 ÷ 144,000
= $1.25 per unit
Therefore,
Budgeted indirect material cost for actual units produced
= $1.25 × 10,800
= $13,500
since,
the budgeted cost for indirect material cost for actual units produced is more than the actual indirect material cost, therefore
the indirect material costs in October is favorable
amount = Budgeted cost - Actual cost
= $13,500 - $13,000 = $500 favorable