Answer:
<em>6 days</em>
<em></em>
Step-by-step explanation:
Let the time taken by Carpenter working alone =
days
Then time taken by apprentice alone = Twice as that of taken by Carpenter = 2
days
Time taken working together = 2 days
Work done in one day working together = 
Work done in one day by Carpenter working alone = 
Work done in one day by apprentice working alone = 
Work done in one day by Carpenter working alone + Work done in one day by Carpenter working alone =
+
= Work done in one day working together = 

Time taken by Carpenter alone to complete the work = 3 days
Time taken by Apprentice alone to complete the work = 3
2= <em>6 days</em>
Answer:
0.08 cubic feet.
Step-by-step explanation:
You have a small marble statue of Mozart that is 10 inches tall and is made of 16 cu. inches of marble.
The original statue in Vienna is 7 feet tall.
First we will convert this to inches as one relation is given in inches.
1 feet = 12 inches
7 feet =
inches
Let the amount of marble used for 84 inches statue be = x
We can relate both the conditions in the following way:


x = 134.40 cubic inches
Now, 1 cubic inch =
cubic foot
So, 134.40 cubic inches =
cubic foot
= 0.0777 cubic feet rounding to 0.08 cubic feet.
You do not make any sense. can you restate your question please
1/8 ( 8x + 15)= 24
x + 1 7/8= 24
x= 24 - 1 7/8
x= 22 1/8
The answer is none of them.