14

Baldwin has negotiated a new labor contract for the next round that will affect the cost for their product Buzz. Labor costs wil

l go from $2.10 to $2.60 per unit. In addition, their material costs have fallen from $6.82 to $5.82. Assume all period costs as reported on Baldwin's Income Statement remain the same. If Baldwin were to pass on half the new costs of labor and half the savings in materials to customers by adjusting the price of their product, how many units of product Buzz would need to be sold next round to break even on the product
Business
1 answer:
harina [27]2 years ago
3 0

Answer:

433 units

Explanation:

Information related to production costs are missing, so I looked for it. I found the following:

current sales price = $17

current fixed costs = $7,242

new labor costs per unit = $2.60, which results in a $0.50 increase

new direct materials cost per unit = $5.82, which results in a $1 decrease

total variable costs per unit = $8.42

Baldwin plans to pass 50% of the changes in costs to its customers:

  • Increase $0.25 due to higher labor costs
  • decrease $0.50 due to lower materials costs
  • net change = -$0.25

new sales price = $17 - $0.25 = $16.75

contribution margin per unit = $16.75 - $8.42 = $8.33

break even point in units = total fixed costs / contribution margin per unit = $7,242 / $16.75 = 432.36 = 433 units

You might be interested in
Carey, a single taxpayer, purchased a rental house in 2018, which he actively manages. During 2018, Carey had a loss of $14,000
noname [10]

Answer:

$6,000

Explanation:

First, Carey's allowable deductions repersents 'real estate loss allowance. The real estate loss allowance is an allowance or tax reduction made available to taxpayers who are also owners of rental properties in the U.S.

The specific allowance states that if the adjusted gross income of the owner of the rental property  is $100,000 or less, then the taxpayer is allowed a deduction of $25,000. However, this begins to reduce as the adjusted gross income approaches $150,000 and the allowance is completely eliminated when the income exceeds $150,000

Based on this explanation, Carey's Adjusted Gross Income= $138,000, higher than $100,000 but less than $150,000

The calculation= 50% ($150,000- maximum allowable adjusted gross income- $138,000 - Carey's reported adjusted gross income)

=0.50 ($12,000)

= $6,000

7 0
2 years ago
Scenario 13-1 Korie wants to start her own business making custom furniture. She can purchase a factory that costs $400,000. Kor
viktelen [127]
The answer is C.$3,000
4 0
2 years ago
Sharp Company manufactures a product for which the following standards have been set: Standard Quantity or Hours Standard Price
marin [14]

Answer:

1a) Actual Cost per foot = 6$

1b) Materials Price variance = 7530

1b) Spending Variance = 10830

2a) Standard Rate = 7.5 USD

2b) Standard Hours = 4804 hours

2c) Standard hours allowed = 2.09

Explanation:

As usual, let's sort out the data given:

1. For direct materials:

a) Compute the actual cost per foot of materials for March.

For actual cost per foot for materials for march. We need to find the actual quantity first. so, we will come back to it.

Data Given:

Units Produced = 2,290

Standard Quantity for Direct material = 3 feet

Standard Quantity for Direct materials = 3 x 2,290 = 6870 feet

Standard Price per foot = 5 USD

Standard Total Units =  6870

Total Price = 5 x 6870 = 34350 USD

But

Actual Price = unknown

Actual Quantity = Unknown

Actual Cost = 45,180$ company purchased the direct materials at that cost.

Material Quality Variance = Standard Price x (Actual Qty - Standard Qty)

Here in this equation, we know all the quantities except Actual Qty. let's make it subject to calculate it.

Actual Qty = 3,300/$5 + 6870

Actual Qty = 7,530

Now, as we have Actual Quantity, we can calculate the part a of part 1.

So, let's calculate a.

a) a) Compute the actual cost per foot of materials for March.

Actual cost per foot = Direct Material Cost / Actual Qty

Actual Cost per foot = 45,180/7530

Actual Cost per foot = 6$

Let's move on to part 1 b.

b) Compute the price variance and the spending variance.

Formula to calculate the Materials Price Variance is as follows:

Materials Price Variance = Actual Qty x( Actual Price - Standard Price)

Materials Price Variance = 7530 x ( 6 - 5)

Materials Price variance = 7530

Now, we have to calculate the spending variance and the formula is as follows:

Spending Variance = (Actual Price x Actual Qty) - (Standard Qty x Standard Price)

Spending Variance = (6 x 7530) - ( 6870 x 5)

Spending Variance = 10830

Let's move on to part 2 a.

a) Compute the standard direct labor rate per hour:

Formula :

Labor rate variance = (Standard Rate - Actual Rate) x Actual Hours

Labor rate variance = Labor spending variance - Labor efficiency variance

Labor rate variance =   3130 - 780 = 2350

In this equation, we know all the quantities but we have to find Standard rate so make it subject.

Standard Rate = 2350/4700 + 7

Standard Rate = 7.5 USD

b. Compute the standard hours allowed for the month’s production.

Labor Efficiency Variance = Standard rate x ( Actual hours - Standard Hours)

In this part, we need to find the standard hours.

let's make it the subject.

Standard hours = 780/7.5 + 4700

Standard Hours = 4804 hours

c. Compute the standard hours allowed per unit of product.

Standard hours allowed can be found by plugging in the values in the following formula.

Formula:

Standard hours allowed = Standard hours / units produced

Standard hours allowed = 4804/2,290

Standard hours allowed = 2.09

6 0
2 years ago
Savannah Factory applies manufacturing overhead based on direct labor cost. Information concerning manufacturing overhead and la
vfiekz [6]

Answer:

$179,950

Explanation:

For determining the overhead applied first we have to find the predetermined overhead rate based on the estimated cost which is shown below:

Predetermined overhead rate is

= Estimated overhead cost ÷ estimated direct labor cost

= $174,000  ÷ $87,000

= $2

Now the applied overhead is

= Predetermined overhead rate × actual direct labor cost

= $2 × $89,975

= $179,950

We simply applied the above formula so that the overhead applied could come

6 0
2 years ago
Darren's discount Motel offers a 27% discounted rate for stays of a week of more. If you stay for eight nights and the usual tat
Dvinal [7]

Discount rate = 27%

Rate before discount = $125 per night

Rate after discount = 125-27%of 125

= 125-33.75 = $91.25

Total nights = 8

Total amount to be paid = 91.25*8 = $730 (answer)

6 0
2 years ago
Other questions:
  • As jamal's income rises, his demand for pizza does not change. it follows that, for jamal, pizza is a(n)
    12·1 answer
  • Marco owns the following portfolio of stocks. What is the expected return on his portfolio?
    11·1 answer
  • A small manufacturing firm uses roughly 3400 pounds of chemical dye a year. Currently the firm purchases 300 pounds per order an
    6·1 answer
  • Last year, Twins Company reported $750,000 in sales (25,000 units) and a net operating income of $25,000. At the break-even poin
    11·1 answer
  • After eating four slices of pizza, you are offered a fifth slice for free. You turn down the fifth slice.
    10·1 answer
  • The accounts in the ledger of Monroe Entertainment Co. are listed below. All accounts have normal balances. Accounts Payable $48
    5·1 answer
  • Excavation, Inc., uses explosives to prepare land for construction projects. Strict liability is imposed on this activity becaus
    15·1 answer
  • PLEASE HELP....WILL GIVE BRAINLIST
    11·1 answer
  • A key objective for a retail layout is to A. expose customers to​ high-margin items. B. balance​ low-cost storage with​ low-cost
    10·1 answer
  • Novak Corp. issued 2,000 8%, 9-year, $1,000 bonds dated January 1, 2022, at face value. Interest is paid each January 1.
    8·1 answer
Add answer
Login
Not registered? Fast signup
Signup
Login Signup
Ask question!