Percent means per one-hundred
300(10/100)=30
So 30 of the 300 workers were satisfied with their benefits.
Answer:
the answer would be 90
Step-by-step explanation:
100 giants fills 5/8 (100/160) of the theater leaving 3/8 of the theater for the elves.
3/8 times 240 elves is 90 elves.
If there were 150 elves that would also be 5/8 filled plus the original 5/8 filled with 100 giants! Some elves might suffer!!!
Answer:
- 4099 yes
- 4110 no
- 5909 no
- 5011 yes
Step-by-step explanation:
The digits will be related by a factor of 10 if they are the same digit. 4099 and 5011 have the same digit in the tens and ones places. 4110 and 5909 do not.
We are given that 76 persons can complete the job in 42 days.
We need to find the number of days will 56 persons do the same job.
Let us assume that in x number of days will 56 persons do the same job.
Number of days taken by 1 person to complete same work = 76 × 42 =3192 days.
56 person will take =
= 57.
<h3>
Therefore, 57 days will 56 persons do the same job.</h3>