Answer:
Risk on the critical path should be given higher priority than activities that are not part of the critical path, or that have a positive slack.
This is because incurring in a riks that is on the critical path can seriously alter the schedule of a project, to the point that the project could be delayed or put off.
Answer:
B. Grouting
Explanation:
These are the options for the question;
A. Epoxy resin
B. Grouting
C. Tensioning
D. Ranging
In the case of dormant cracks wider than about 1m, it is more economical to use grouting method.
Grouting techniques is a techniques that is achieved by removal of dirt or unwanted substance from the crack of the the faulty part and then grouting of the crack after which the surface is sealed by sealants. It should be noted that grouting is economical than other methods such as surface treatment.
Answer:
c) $5,000
Explanation:
Kansas Plating Company
Cost of Goods Manufactured.
DM used $40,000
Add Direct labor $70,000
Add Overhead $180,000
Total Manufacturing Costs 290,000
Work in Process Inventory
Add Begin. Inv. 5000
Avail. for mfg. 295,000
Less End. Inv. 3,500
0
Cost of goods mfg 260,000
As the beginning balances of materials direct labor and FOH are given we add these to get total manufacturing costs and also the ending balances are given of Cost of Goods Manufactured and ending Inventory we calculate backwards to get to the Work In Process opening Inventory.
<span>Yooshuh is in the process of strategic planning. She is developing the companies short term goals, those things that she believes can be reached within the next year as well as identifying the milestone dates to which she thinks these can be achieved.</span>