Answer:
11.2 containers
Explanation:
The computation of the number of kanban connectors needed is given below:
= (Lead time demand + Safety stock) ÷ Container size
where,
Demand during Lead time demand is
= 1,400 units × 3 days
= 4,200 units
Container size = 500 connectors
Safety Stock is
= 1 day × 1,400 units
= 1,400 units
So, the number of kanban connectors needed is
= (4,200 units + 1,400 units) ÷ (500 units)
= 11.2 containers
We simply used the above formula
Answer:
meal option is cheaper with total cost = $2000 and hall only option is total cost $2700
Explanation:
given data
The meal option = $50 per person.
Hall free = $ 0 per person
total guest = 40
hall-only option = $1,500
external caterer = $30 per person
solution
when we go for meal option than hall free so total cost will be as
total cost = total guest × $50 per person
total cost = 40 × $50
total cost = $2000
and
when we go for hall only option than total cost will be
total cost = total guest × external caterer charge + hall-only option
total cost = 40 × $30 + $1500
total cost = $2700
so
meal option is cheaper with total cost = $2000 and hall only option is total cost $2700
Answer: best practices
Explanation: In context of Enterprise resource planning, the most efficient ways to conduct business activities are termed as best practices.
Best practices are those alternatives of doing an activity which are superior to other alternatives as they results in better conclusions than other options. These are generally seen as a techniques or a standard method of performing an activity.
By definition, opportunity cost is the cost of the next alternative that you gave up because you choose another one. In this case, there are two alternatives: the closer gas station and the farther gas station. Because you chose the cheaper but farther gas station, then the opportunity cost is $2.50 for the closer gas station.
<span>A key economic factor that will affect your career opportunity is supply. Supply goes hand in hand with demand with any type of economy. Sometimes the demand is there and the supply isn't or vice versa. The supply is needed for any job to be available to begin with.</span>