<span>(x + 2)</span>·<span>2 = a
(1 + 2)</span>·2 = a
3·2 = a
a = 6
Standard deviations of the four activities of the critical path are 1,2,4,2.
Standard deviation of this critical path = Sum of square root of variance of this corresponding critical path
Standard deviation of critical path 



Now we need to find the probability that the project will completed in 38 weeks given that its expected completion time is 40 weeks.
That is, we need to find P(X<38) :


Probability 
Thus the probability that the project will be completed in 38 weeks is 0.34.
Answer:
Adam is taking the original price minus 75% of the original price, while Rena is taking the original price times 25% which is what you would be paying. Both are correct but Renas is more efficient.
Step-by-step explanation: