Well...if he earns $75 an hour....and he worked for 20 hours...that's
75 * 20 which = 1500
Now it says he also earns a flat fee....since the question states he billed the client 1800...and he only earned 1500 of it...that must mean that his flat fee would be
1800 - 1500 = 300
So his flat fee is 300...and his variable charge...is 75x (75 dollars per hour)
in an equation...this would look like
C(x) = 75x + 300
<span>Bank of America, with 14,058 million common shares outstanding in 2015, and with dividends of $0.05 paid 4 times per share in 2015, the dividends paid overall in 2015 was $2,812 million.</span>
Answer:
Order size= $57.61 per machine hour
Explanation:
Giving the following information:
Order size:
Estimated total overhead= $581,866
Estimated total machine hours= 10,100
<u>To calculate the predetermined manufacturing overhead rate we need to use the following formula:</u>
Predetermined manufacturing overhead rate= total estimated overhead costs for the period/ total amount of allocation base
Order size= 581,866 / 10,100
Order size= $57.61 per machine hour
Answer:
e. A, 6,000; B, 6,000.
Explanation:
At the beginning of the process Materials A are added. Therefore it won't matter if the process is 80% or less/more is complete, the materials A have already been added and would be equivalent to the ending work-in-process inventory i.e. 6,000 units.
Materials B are added when the units are 75% complete. Since the ending work-in-process are 80% complete, then this means that the Materials B equivalent to 6,000 units have already been added to the ending inventory.
Hence, both materials A and B have been added to the ending work-in-process inventory for 6,000 units. Therefore, option E is correct.
Answer:
170,146
Explanation:
$250,000 / (1.08)5= 170,146