The given function is
f(x) = 4x - 3/2
where
f(x) = number of assignments completed
x = number of weeks required to complete the assignments
We want to find f⁻¹ (30) as an estimate of the number of weeks required to complete 30 assignments.
The procedure is as follows:
1. Set y = f(x)
y = 4x - 3/2
2. Exchange x and y
x = 4y - 3/2
3. Solve for y
4y = x + 3/2
y = (x +3/2)/4
4. Set y equal to f⁻¹ (x)
f⁻¹ (x) = (x + 3/2)/4
5. Find f⁻¹ (30)
f⁻¹ (30) = (30 + 3/2)/4 = 63/8 = 8 (approxmately)
Answer:
Pedro needs about 8 weeks to complete 30 assignments.
50% or 1/2 of 4 is 2 50% or 1/2 of 6 is 3 so then just add them to the respective number since its going up by 50% or 2 in by 3 in \[\frac{ 6 }{ 9}\]
Answer:
Step-by-step explanation:
There is 100 centimeters in 1 meter.
Change the meter to centimeter. Multiply: 2 x 100 = 200
200 cm < 275 cm ∴ is greater by 75 cm