Answer: x1 = 251/26, x2 = -111/26
Step-by-step explanation:
Hi!
As you can see in the figure, the point you are looking for is the intersection of two lines.
The intersection point is found solving this system of linear equations (the point must satisfy both equations):

You can solve it, for example, by the method of substitution:

Then plug x1 into equation 2, and solve for x2:

Then you use the value of x2 to get x1:

Answer: There are 3 strips that can be cut from the roll of ribbon.
Step-by-step explanation:
since we have given that
Length of a ribbon is given by

Length of pieces of ribbon cut into strips is given by

So, we need to find the number of strips that can be cut is given by

Hence, there are 3 strips that can be cut from the roll of ribbon.
<h2>
Answer:</h2>
Ques 1)

Ques 2)

<h2>
Step-by-step explanation:</h2>
Ques 1)
We know that if a graph is stretched by a factor of a then the transformation if given by:
f(x) → a f(x)
Also, we know that the translation of a function k units to the right or to the left is given by:
f(x) → f(x+k)
where if k>0 then the shift is k units to the left
and if k<0 then the shift is k units to the right.
Here the graph of f(x) is transformed into the graph of g(x) by a vertical stretch of 4 units and a translation of 4 units right.
This means that the function g(x) is given by:

Ques 2)
We know that the transformation of the type:
f(x) → f(x)+k
is a shift or translation of the function k units up or down depending on k.
If k>0 then the shift is k units up.
and if k<0 then the shift is k units down.
Here, The graph of the function f(x)=|3x| is translated 4 units up.
This means that the transformed function g(x) is given by:

Answer:
a
b
Step-by-step explanation:
From the question we are told that
The mean is 
The standard deviation is 
Generally 2 year is equal to 24 months
Generally the percentage of total production will the company expect to replace is mathematically represented as

Generally 

Generally from the z-table

So

Converting to percentage

=>
Generally the duration that should be the guarantee period if Accrotime does not want to make refunds on more than 6% is mathematically evaluated as

=> 
From the normal distribution table the z-score for 0.06 at the lower tail is

So

=>