To find the dimensions you can just factor the equation...
x^2+4x-21
x^2-3x+7x-21
x(x-3)+7(x-3)
(x+7)(x-3) and this is equal to LW or WL
And note that x>3 for any possible solution.
According to the triangle sum theorem, all the angles in a triangle must add up to 180 degrees. If we know one angle is already 90, we do 180-90=90. The other 2 angles must add up to 90, exactly.
Answer:
The figures are congruent because a 270° rotation about the origin and then a reflection over the x-axis will map ΔABC onto ΔLMN.
<span>The possible values are less than 4 but greater than –4.</span>
Answer:
the probability that the project will be completed in 95 days or less, P(x ≤ 95) = 0.023
Step-by-step explanation:
This is a normal probability distribution question.
We'll need to standardize the 95 days to solve this.
The standardized score is the value minus the mean then divided by the standard deviation.
z = (x - xbar)/σ
x = 95 days
xbar = mean = 105 days
σ = standard deviation = √(variance) = √25 = 5
z = (95 - 105)/5 = - 2
To determine the probability that the project will be completed in 95 days or less, P(x ≤ 95) = P(z ≤ (-2))
We'll use data from the normal probability table for these probabilities
P(x ≤ 95) = P(z ≤ (-2)) = 0.02275 = 0.023