Answer:
8 hours
Step-by-step explanation:
Job v starts at time 0 and completes at time 3.
Job w starts at time 1 and completes at time 4.
Job x starts at time 4 and completes at time 8.
Job y starts at time 8 and completes at time 10.
Job z starts at time 10 and completes at time 15.
The average completion time is (3 +4 +8 +10 +15)/5 = 8 . . . hours.
_____
<em>Comment on the schedule</em>
Jobs v and x are the only ones completed by the time due. The latest is 8 hours late. If they are scheduled in order of due time, jobs v, w, and y can be completed by the due time; the others will be 4 and 6 hours late.
Answer:
The shape of the pebbles is a result of weathering and deposition.
Step-by-step explanation:
C because you have to divide by m or the members because you are splitting it up or dividing it between the members. And you subtract 95 dollars becuase it was a cost or bill
Answer:
He could have 4 dimes, or 8 nickles, or 1 quater and 3 nickels, or 1 quater with one dime and 1 nickel, or 3 dimes and 2 nickles, or 1 quater with obe nickel and one dime.
Step-by-step explanation:
hope this helps.
Answer:
1 and 3/8 of pizza
Step-by-step explanation:
5/8 + 3/4
3/4 x 2 to get the same denominator as 5/8
5/8 + 6/8 = 11/8
11/8 = 1 3/8