The correct answer is - the number of hours he works at each job.
If we have the number of hours he works for each job separately, then we will be able to take out a percentage of the earnings from both of the jobs separately. We will than get the sum of the percentages if both of them, and have the real amount of George's weekly savings.
Answer:
CCC's new required rate of return is 16.5%
Explanation:
in the first we need to determine the risk free rate using the Capital Asset Pricing Model formula of Miller and Modgiliani as shown below
required return=Rf+beta*(average market return-Rf)
Rf is the risk free rate that is unknown
Beta is 1.5
average market return is 10%
required rate of return is 12%
Rf?
12%=Rf+1.5*(10%-Rf)
12%=Rf+15%-1.5Rf
1.5Rf-Rf=15%-12%
0.5Rf=3%
Rf=3%/0.5
Rf=6%
Average rate of 10% has now increased by 30% i.e 10%*(1+30%)=13%
Required rate of return=6%+1.5*(13%-6%)
=6%+1.5*7%
=6%+10.5%=16.5%
Answer:
Predetermined manufacturing overhead rate= $53,75 per machine hour
Explanation:
Giving the following information:
Order size:
Estimated activity cost= $585,866
Estimated machine hours= 10,900
<u>To calculate the predetermined manufacturing overhead rate we need to use the following formula:</u>
Predetermined manufacturing overhead rate= total estimated overhead costs for the period/ total amount of allocation base
Predetermined manufacturing overhead rate= 585,866/10,900
Predetermined manufacturing overhead rate= $53,75 per machine hour
Answer:
The overhead application rate is 1.8
Explanation:
In the question both the estimated and actual overhead cost , material and labor cost are provided -
ESTIMATED ACTUAL
Overhead cost $396,000 $418,000
Material cost $410,000 $413,200
Direct cost $220,000 $224,000
Overhead application rate can be calculated by dividing the total budgeted overhead cost by direct labor cost.
= Budgeted overhead cost / direct labor cost
= $396,000 / $220,000
= 1.8