answer.
Ask question
Login Signup
Ask question
All categories
  • English
  • Mathematics
  • Social Studies
  • Business
  • History
  • Health
  • Geography
  • Biology
  • Physics
  • Chemistry
  • Computers and Technology
  • Arts
  • World Languages
  • Spanish
  • French
  • German
  • Advanced Placement (AP)
  • SAT
  • Medicine
  • Law
  • Engineering
Tasya [4]
2 years ago
14

Your project to obtain charitable donations is now 30 days into a planned 40-day project. The project is divided into three acti

vities. The first activity is designed to solicit individual donations. It is scheduled to run the first 25 days of the project and to bring in $25,000. Even though we are 30 days into the project, we still see that we have only 90 percent of this activity complete. The second activity relates to company donations and is scheduled to run for 30 days starting on day 5 and extending through day 35. We estimate that, even though we should have 83 percent (25/30) of this activity complete, it is actually only 50 percent complete. This part of the project was scheduled to bring in $150,000 in donations. The final activity is for matching funds. This activity is scheduled to run the last 10 days of the project and has not started. It is scheduled to bring in an additional $50,000. So far, $175,000 has actually been brought in on the project.
Calculate the Schedule Variance, Schedule Performance Index, and Cost (actually value in this case) Performance Index. How is the project going? (Hint: Note that this problem is different since revenue rather than cost is the relevant measure. Use care in how the measures are interpreted.)
Business
1 answer:
adell [148]2 years ago
4 0

Answer:

1. schedule variance = -$52,500

2. SPI = 0.65

3. CPI = 0.56

Explanation:

to get the solution, we calculate for BRWS and BRWP

first we calculate the budgeted revenue of the work scheduled for each activity using this formula:

<u>budgeted</u><u> </u><u>revenue</u><u> </u><u>*</u><u> </u><u>planned</u><u> </u><u>completion</u>

A = 25,000 x 100percent

= $25000

B = 150,000 x (25/30) percent

= $125000

C = 50000 x 0percent

= 0$

total = $25000+$125000+$0

= $150000

Next we calculate budgeted revenue of work performed (brwp)

<em>calculated using this formula</em>:

<u>budgeted revenue x actual </u><u>completion</u>

A = 25000 x 90percent

= 22500 dollars

B = 150000 x 50percent

= $75000

C = 50000 x 0%

= $0

total = 22500 + 75000 + 0

= $97500

<u>1</u><u>.</u><u> </u><u>schedule</u><u> variance</u><u> </u><u>=</u><u> </u><u>BRWP </u><u>-</u><u> </u><u>BRWS</u>

<u>=</u><u> </u>$97500 - $150000

= -$52500

<em>we </em><em>have</em><em> a</em><em> </em><em>negative</em><em> </em><em>schedule</em><em>,</em><em> </em><em>telling</em><em> </em><em>us </em><em>that </em><em>the </em><em>project</em><em> </em><em>is </em><em>behind</em><em> </em><em>schedule</em>

<em>2</em><em>.</em><em> </em><u>schedule</u><u> </u><u>performance</u><u> </u><u>index </u><u>=</u><u> </u><u>revenue</u><u> </u><u>of </u><u>work </u><u>performed</u><u> </u><u>divided </u><u>by </u><u>revenue</u><u> of</u><u> work</u><u> </u><u>schedule</u>

<u>=</u><u> </u>97500/150000

= 0.65

3. <u>cost price index = revenue of work performed divided by actual revenue</u>

= 97500/175000

= 0.56

4. <u>how </u><u>the </u><u>project</u><u> </u><u>is </u><u>going</u><u>:</u>

the schedule performance index (SPI) is 0.65 which is less than 1. this is to say that the project is doing better than planned revenue when we talk of revenue

You might be interested in
Regan company operates its factory on a two-shift basis and pays a late-shift differential of 15%. regan also pays a premium of
victus00 [196]
The <span>amount of direct labor should Regan charge to work-in-process is the wages at base direct-labor rates, which is $325,000.00.  Shift Differentials and Overtime Premiums are not included,</span>
3 0
2 years ago
On December 1, 2018, your company borrowed $15,000, a portion of which is to be repaid each year on November 30. Specifically, y
tino4ka555 [31]

Answer:

Explanation:

The loan will be reported in the December 31, 2019 and 2018, balance sheets, is shown below:-

                              Balance sheet(Partial)

                                                 As of December 31

                                                      2016        2015

Current liabilities

Current portion of long term debt $3,000   $2,000

Long term liabilities

Long term debt                              $10,000   $13,000

Total liabilities                                $13,000     $15,000

On December 2018 we represent the current liability of $2,000 loan because of year 31 December 2019 within of one year and the left portion of the loan represent as long term liability because it is not within one year from the balance sheet.

On December 2019 Loan remains outstanding $13,000 ($2,000 repaid on November 2019) from this amount, on November 30, $3,000 is due. So, $3,000 should be represented as current liability and the left balance $10,000 represented as long term debt.

8 0
2 years ago
​Lori, who is risk​ averse, has two pieces of​ jewelry, each worth​ $1,000. She plans to send them to her​ sister's firm in Thai
Mkey [24]

Answer:

The correct answer is the option E: higher if she sends the jewelry to Thailand in separate boxes because she's risk averse.

Explanation:

On the one hand, if Lori is <em>risk averse</em> then that means that she tends to prefer the less risk that can be in the moment of making a decision without given importance to what she can make of that decision.

On the other hand, the <em>expected utility</em> hypothesis states that Lori will choose the option that will have a greater utility according to the situations.

In conclussion, Lori will choose to send the jewelry to Thailand in separate boxes because she is risk averse and she will prefer to expend more money and lower the risks and by doing that she will have a higher expected utility.

3 0
2 years ago
Owen expects to receive at the end of next year from a trust fund. If a bank loans money at an interest rate of ​, how much mone
Nezavi [6.7K]

Answer: a) $18,605

Explanation:

The amount he can borrow today will be an amount that when grown at a rate of 7.5% per year will equal $20,000 in a year.

20,000 = Amount + ( Amount * rate * time)

20,000 = Amount + (7.5% * Amount)

2,000,000 = 1.075 * Amount

Amount = $18,605

4 0
2 years ago
Jessica weighs 125 lbs. She rode a bike at 17 mph for 25 minutes. What is the calorie cost of this activity?
Tomtit [17]

Answer: 178 calories

Explanation:

From the question, we are informed that Jessica weighs 125 lbs and that she rode a bike at 17 mph for 25 minutes. It should be noted that 17 mph is thesame as 0.057 cal/lb/min.

Therefore, the calorie cost of this activity will be:

= 0.057 x 125 = 7.125

We then multiply 7.125 by the number of minutes used. This will be:

= 7.125 x 25

= 178 calories

3 0
2 years ago
Other questions:
  • You are working part-time at a road construction firm. your boss knows you are learning some statistics in your classes this sem
    6·1 answer
  • "a monopolist earns $50 million annually and will maintain that level of profit indefinitely, provided no other firm enters the
    15·1 answer
  • Barnes Company sells two products, X and Y. For the coming year, Barnes predicts sales of 5,000 units of X and 10,000 units of Y
    11·1 answer
  • A firm has a profit margin of 12 percent; total asset turnover of 0.55 and an equity multiplier of 2.2. What is the firm's ROA a
    9·1 answer
  • The following are sales revenues for a large utility company for years 1 through 11. Forecast revenue for years 12 through 15. B
    14·1 answer
  • KaiLynn has total job benefits of $41,000 per year in her sales job. She pays $63 each month for a cell phone for work. She is a
    5·1 answer
  • Ryan Co. sells major household appliance service contracts for cash. The service contracts are for a 1-year, 2-year, or 3-year p
    10·1 answer
  • Mar. 29 Received a $30,000, 60-day, 5% note dated March 29 from Karie Platt on account.
    12·1 answer
  • Sarah notices a sign in the window of a clothing store advertising a major sale on coats. realizing that she needs a new coat, s
    9·1 answer
  • How might a Product Owner (PO) adjust team events to take advantage of this capability and promote the flow of value?
    11·1 answer
Add answer
Login
Not registered? Fast signup
Signup
Login Signup
Ask question!