We have this following information
30-seconds ad = $146000
The manufacturer wants to use one slot of 30-second per segment
Total segment = 20 segment
Total campaign cost = 20×146000 = $2,920,000
Answer:
989000
Step-by-step explanation:
Divide 2,967 ÷ 0.003
Standard deviations of the four activities of the critical path are 1,2,4,2.
Standard deviation of this critical path = Sum of square root of variance of this corresponding critical path
Standard deviation of critical path 



Now we need to find the probability that the project will completed in 38 weeks given that its expected completion time is 40 weeks.
That is, we need to find P(X<38) :


Probability 
Thus the probability that the project will be completed in 38 weeks is 0.34.
Answer:
The square root of terms separated by addition and subtraction cannot be calculated individually.
Step-by-step explanation:
Answer:
A circle can intersect a parabola in
1. One point [ when circle just touches the parabola]
2. Two points [ When circle cuts the parabola in two distinct points. ]
3. Three points [Circle just touches at one point and cuts the parabola in two distinct points]
4. Four points [ Either parabola or circle meeting each other or crossing at four distinct points]