Answer:
The equal employment opportunity commission trust me
Answer:
The production exhibit both scope economics and scale economics. They are not mutually exclusive.
Explanation:
Looking at the scenario critically, we will clearly see the tendency of a scope economics. Scope economics basically hinges on getting a competitive advantage, essentially because of producing in large quantities and numbers. Riverside Ranger logo T-shirts exhibits this as it produce its products in large numbers, producing 1000 pieces of a particular design in 1 hour.
In same breath, we also have the scale economics exhibited by the organization. Taking a deeper look at the cost representation, we will see that the average cost tend to reduce as the production increases. Thus, an economic of scale is achieved here by leveraging on the mass and swift production style of Riverside Rangers logo T-shirts.
Answer:
The correct answer is C
Explanation:
Project scope is the one which is defined as the how the goals as well as objectives of the project are defined. This states the lists that goals, what the deliverables would be, the tasks required to make the deliverables, what the costs or expense for that would be and the deadlines. In short, it is the parameters of the whole project.
So, the one which will not be included in the planning process of the project scope is how the case of the business would be created.
Answer:
$200,000
Explanation:
This involves revenue recognition based on percentage of work completed (cost to completion technique). Revenue to be recognized per time is assessed based on the level of cost incurred compared with the total cost to be incurred.
Given that the total approved budget for the project is $600,000, If at the end of the first three weeks of work, $160,000 has been spent, and five miles of road have been completed for a a 15-mile road, the earned value of the project at the end of the first three weeks
= 5/15 * $600,000
= $200,000
Answer:
5.5 Hours
Explanation:
The main difference among both the drivers is the number of jobs and the difference of working hours can only be determined by adding number of jobs. Sofia has two more jobs compared to victor. Following is the method to calculate the working hours:
4+0.75(2)=5.5 hours
Sofia is expected to work for 5.5 hours