Standard deviations of the four activities of the critical path are 1,2,4,2.
Standard deviation of this critical path = Sum of square root of variance of this corresponding critical path
Standard deviation of critical path 



Now we need to find the probability that the project will completed in 38 weeks given that its expected completion time is 40 weeks.
That is, we need to find P(X<38) :


Probability 
Thus the probability that the project will be completed in 38 weeks is 0.34.
Answer:
Reference The length of time Y necessary to. ... construction of houses has an exponential distribution with mean 10 hours. The formula C = 100 + 40Y + 3Y 2 relates the cost C of completing this operation to ... Find the mean and variance of C. ... The length of time necessary to complete a key operation in the construction of ...
Step-by-step explanation:
Answer:
The one that belong in the dividend bracket is the volume for A. The one that belongs in the divisor bracket is volume C.
Step-by-step explanation:
That's my explanation on what the answer is supposed to be.
Answer:
a) 23.76%
b) 7.8%
Step-by-step explanation:
a) probability that a failure is due to loose keys.
loose key failure (27%) comes under mechanical failure(88%)
hence, probability that a failure is due to loose keys= 0.27×0.88= 0.2376= 23.76%
b) probability that a failure is due to improperly connected wire which comes under electrical failure = 0.12×0.13
probability that a failure is due to poorly welded wires which comes under electrical failure= 0.52×0.12
now, the probability that a failure is due to improperly connected or poorly welded wires. = 0.12(0.52+0.13)= 0.078= 7.8%