Answer:
A) 
B) 
Explanation:
Given:
- temperature of air,

- temperature of lungs,

- specific Heat exchanged from the lungs ,

- specific heat of air,

- mass of 1 L air,

- breath rate,

A)
Now,
amount of heat needed to warm the air of lungs to the body temperature:



B)
Amount of heat lost per hour:
<u>No. of breaths per hour:</u>



<u>Now the total loss of energy in 1 hr.:</u>



Answer:
Velocity, v = 2.50 m/s
Explanation:
Given that,
Mass of the ball, m = 7.26 kg
Height above the ground, h = 2.1 m
Mechanical energy of the ball, T = 172.1 J
To find,
The velocity of the ball at the given point.
Solution,
The sum of potential energy and the kinetic energy is called the mechanical energy of an object. It is given by :

K is the kinetic energy
P is the potential energy

On rearranging the above equation,


v = 2.50 meters
Therefore, the velocity of the ball at the given point is 2.50 m/s.
Initial speed of the coin (u)= 0 (As the coin is released from rest)
Acceleration due to gravity (a) = g = 9.81 m/s²
Time of fall (t) = 1.5 s
From equation of motion we have:

By substituting values in the equation, we get:
v = 0 + 9.81 × 1.5
v = 14.715 m/s
Speed of the coin as it hits the ground/Final speed of the coin = 14.715 m/s
<h2>Answer:</h2>
<u>This term shows the </u><u>mass of the space shuttle</u>
<h2>Explanation:</h2>
We know that the mass of the Earth is 5.972 × 10^24 kg. Similarly the sum of mass of earth and the mass of shuttle must be a greater number as compared to the number given. It simply means that the mass of earth is itself 5.972 × 10^24 kg and the value given is 3 × 105 kg so it is obvious that if was the sum then it must be greater than the mass of earth. Therefore we can say that this not the mass of earth, neither the sum of mass of earth and shuttle, but this is only the mass of space shuttle which is the last multiple choice.
Answer:
90.77%
its capacity utilization rate for the month is 90.77%
Explanation:
The capacity utilisation rate can be expressed mathematically as;
Capacity utilisation rate = capacity used/Best operating level × 100%
Given;
Total Number of production time = 205hours
Production output/capacity used = 21400 units
Best operation rate = 115units/hour
Best operation output for the month of July( at best operation level )
=115units/hour × 205 hours = 23575 units
Capacity utilisation rate = 21400/23575 × 100%
= 90.77%